October 2026 Building Campaign Update: Issuing the Contractor RFP & Celebrating Your Faithfulness!

Published October 20, 2026

Dear Christ Church Family,

  

As the leaves begin to turn and we step into the beauty of autumn, our hearts are overflowing with gratitude for the Lord’s steady guidance and for your joyful, sacrificial faithfulness. Every step of this journey reminds us that we are not merely constructing walls and laying foundations; we are preparing spaces where generations will encounter Jesus, grow in community, and go forth to serve.

  

Our Building Team gathered on the evening of Monday, October 13, to worship in prayer, review our growing campaign funds, and take significant logistical steps forward. We are thrilled to share this month's milestones with you!

  

Don’t Have Time to Read the Whole Email? … A Summary

  
      
  • Grateful Financial Momentum: September saw $30,941.12 in campaign giving and $1,318.78 earned in interest, bringing our total Building Fund balance to $282,390.00 as of September 30 (with October already showing strong early momentum!).

      
  •   
  • Contractor RFP Launching: On October 15, we are officially issuing our Request for Proposals (RFP) to a curated list of top regional design-build contractor teams, keeping us on track to review proposals in November and select our Phase 1 partner by December.

      
  •   
  • City & Site Planning Alignment: We are finalizing our Comprehensive Development Review submission for the Planning Commission on October 22, ensuring our site conditions, mature tree canopy preservation, and local stormwater standards align with city ordinances.

      
  •   
  • Target Construction Schedule: Our timeline remains on target to complete preliminary design work through spring 2027, with a goal of breaking ground in Summer 2027.

      
  •   
  • Giving Clarification: You are warmly encouraged to begin giving toward your campaign pledge now! If you have any questions regarding your quarterly giving statement or fund designations, our office is here to help.

      
  •   
  

Celebrating Your Generosity: Financial Update

  

The generosity of our church family continues to be a profound source of encouragement. Through monthly gifts, commitments, and year-end contributions, your support ensures we step into each phase with solid footing and fiscal discipline.

  

Here is where our building campaign finances stood through the close of September:

                                                    
MetricAmount
Gifts Received (Sept 1 – Sept 30, 2026)$30,941.12
Interest Earned in High-Yield Accounts (Sept)$1,318.78
Project Expenses Incurred (Sept)$0.00
Total Building Fund Balance (as of Sept 30, 2026)$282,390.00
  

Note: These figures reflect the books as of September 30. October giving is already matching pace, thanks to ongoing pledges and periodic transfers (including tax-smart qualified charitable distributions from IRAs).

  

A Helpful Note Regarding Your Giving Statements

  

Quarterly contribution statements were recently emailed. If you have been wondering, "Can I start giving to my pledge now?"—the answer is yes, absolutely!

  

A few members noted seeing both "Building Fund" and "Building Campaign" line items on their statements due to how legacy online options were set up. Rest assured, gifts directed to either fund apply directly toward our expansion project and your campaign commitment. If you notice any discrepancy or need help adjusting your recurring gift, please reach out to Emily in the church office, and she will gladly adjust it for you.

  

Progress & Key Updates: What Happened This Past Month

  

1. Issuing the Design-Build Contractor RFP

  

This week marks a major project milestone. Following thorough preparation and template reviews, we are officially issuing our Request for Proposals (RFP) on October 15, 2026, to an invited group of qualified, reputable regional design-build firms.

  
      
  • Mandatory Contractor Walkthrough: Thursday, October 22, at 3:00 PM at the Family Life Center.

      
  •   
  • Proposal Submission Deadline: Thursday, November 5, at 2:00 PM.

      
  •   
  • Blind Review & Stewardship: To ensure complete fairness and objective evaluation, cost proposals will be sealed and reviewed after assessment of returned proposals.

      
  •   
  • Selection Roadmap: Finalist interviews will be conducted around December 8, with the goal of selecting our Phase 1 Design-Build partner and executing a pre-construction contract before the end of the year.

      
  •   
  

2. Planning & Zoning (CCPC) & Site Review

  

Following a brief shift due to local fall breaks, our civil engineering package will be submitted for internal comprehensive development review with local utilities and agencies (BGMU, Public Works, Spectrum, etc.) on October 21, followed by our formal submission on October 22, 2026.

  
      
  • Stormwater Stewardship: We reviewed Bowling Green’s updated stormwater regulations. Because Christ Church sits on a spacious 10-acre campus, we will manage and retain our stormwater on-site through our natural retention areas, ensuring full environmental compliance without incurring costly off-site fee-in-lieu assessments.

      
  •   
  • Development Conditions & Natural Beauty: Our application sets comfortable building height guidelines (up to 50 feet, which easily accommodates our sanctuary design while exempting any future steeple features) and commits to preserving our mature, healthy tree lines and woodland areas behind the Family Life Center and along Brandy Circle.

      
  •   
  • Geotechnical Due Diligence: Due to our regional karst geography, the team is proactively working with our civil engineer to conduct testing during Phase 1 to verify subsurface bedrock conditions prior to heavy foundation design.

      
  •   
  

Next Steps & Roadmap

  

Here is what is on the horizon over the next 60 days:

  
      
  1. October 15–28: Distribution of the RFP to contractors, hosting the on-site walkthrough on October 22, and fielding contractor clarifications.

      
  2.   
  3. November 5–10: Electronic proposal receipt and initial Building Team evaluation at our regular November meeting.

      
  4.   
  5. Early December: Contractor finalist interviews and presenting our recommended Phase 1 pre-construction partner to the Christ Church Lead Team.

      
  6.   
  7. Looking Ahead to 2027: Phase 1 design, space planning, and budget refinement will run through the winter and spring, preparing detailed construction numbers for full congregational review, leading toward our target construction start in Summer 2027.

      
  8.   
  

Call to Prayer: How You Can Partner This Month

  

More than mortar, stone, and architectural drawings, this project is built upon the faithful prayers of our people. We invite you to lift up these specific requests with us over the coming weeks:

  
      
  • Wisdom & Discernment: Pray for the Building Team as we review contractor proposals in November, that the Lord would make clear the right design-build team whose values, craftsmanship, and vision align with Christ Church.

      
  •   
  • Favor in Municipal Approvals: Pray for our Planning & Zoning submittal on October 22 and the various utility reviews, asking for smooth, timely approvals across all local agencies.

      
  •   
  • Unity & Sustained Generosity: Pray for continuous unity within our church family, for continued health and provision across every household, and for God to use this season of giving to stretch our faith and deepen our love for one another.

      
  •   
  

Closing & Project Hub Information

  
      
  • Next Building Team Meeting: Monday, November 10, 2026.

      
  •   
  • Building Project Hub: You can view previous updates, architectural sketches, campaign brochures, and FAQs anytime at www.christchurchbg.org by clicking "Building Project Hub" at the top of any page.

      
  •   
  

If you have questions, feedback, or would like to learn more, please don’t hesitate to connect with our Campaign Co-Chairs or our Building Team Chair:

  
      
  • Betsy Kullman or Mike Gardner (Campaign Co-Chairs)

      
  •   
  • Preston Withers (Building Team Chair)

      
  •   
  • Church Office: (270) 842-4343

      
  •   
  

With joyful expectation in Christ,

  

The Christ Church Building Team